One human cremation system supplied for the City of Bacoor Columbarium & Crematorium at Public Cemetery 3, Barangay Molino 2, Cavite, with delivery, installation, operator training and a two-year warranty.


City of Bacoor Columbarium and Crematorium exterior at Public Cemetery 3, Molino 2
City of Bacoor Columbarium & Crematorium at Public Cemetery 3, Barangay Molino 2, Cavite

PROJECT AT A GLANCE


Client — City Government of Bacoor

Project — City of Bacoor Columbarium & Crematorium

Location — Public Cemetery 3, Barangay Molino 2, Bacoor City, Cavite

Equipment — One (1) lot Human Cremation System

Application — Municipal Public Crematorium

Living Roots Scope — Supply, delivery, installation and operator training

Warranty — Two (2) years

Facility Milestone — Completed and blessed May 16, 2024


The May 16, 2024 date refers to the overall LGU facility. A separate Living Roots equipment turnover date and the equipment model have not been confirmed.


PROJECT INTRODUCTION


Human Cremation System for Bacoor City


The City Government of Bacoor developed its Columbarium and Crematorium at Public Cemetery 3 in Barangay Molino 2, Bacoor City, Cavite. The local-government facility combines a public crematorium with related memorial and columbarium spaces.


Living Roots Philippines supplied one lot of human cremation equipment for the project, including delivery, installation and operator training. The equipment package carried a two-year warranty.


City of Bacoor Columbarium and Crematorium entrance signage Public Cemetery 3
Facility signage identifying Public Cemetery 3 in Barangay Molino 2, Bacoor City

THE CLIENT REQUIREMENT


An Installed and Supported Cremation System for an LGU Facility


Municipal crematorium projects require coordinated equipment procurement and facility integration. The equipment must be delivered and installed within a dedicated cremation area, and the designated operating team needs training before routine use.


For Bacoor City, the specified Living Roots package covered one lot of human cremation equipment, supply, delivery, installation, training and a two-year warranty. The scope is specific to the cremation equipment; it should not be confused with construction of the columbarium, chapel or cemetery complex.


Bacoor Memorial Chapel exterior at Public Cemetery 3
Bacoor Memorial Chapel within the municipal cemetery complex

THE EQUIPMENT


One Lot of Human Cremation Equipment


The core of the Living Roots engagement was one lot of human cremation equipment for the City of Bacoor crematorium.

For related equipment information, see Living Roots Philippines’ human cremation machine offering.


FACILITY INTEGRATION


A Dedicated Crematorium Within a Larger Civic Development


The Bacoor complex includes a prominent columbarium building and a memorial chapel, alongside the crematorium.


Front facade of City of Bacoor Columbarium in Molino 2
City of Bacoor Columbarium building facade

Bacoor crematorium interior with City Government seal and chamber opening
Municipal crematorium interior showing the City of Bacoor seal and cremation chamber opening

PROJECT IMPLEMENTATION


Supply, Delivery, Installation and Training


Living Roots’ contracted project package included supply and delivery of the human cremation system, installation at the Bacoor facility, and training for designated personnel. Its standard equipment delivery process also encompasses commissioning, operational checks, turnover and after-sales technical support; project-specific dates and test records are not stated here.


The supplied system was covered by a two-year warranty. This after-sales provision is an important consideration for public facilities planning long-term equipment support.


Personnel handling a covered trolley at Bacoor crematorium facility
Personnel handling a covered trolley in the crematorium room; photograph documents the facility environment

COMPLETED PROJECT


Facility Completion and Blessing on May 16, 2024


The City Government of Bacoor completed and blessed its Columbarium and Crematorium project at Public Cemetery 3 on May 16, 2024. That public facility milestone is distinct from the equipment supplier’s separate delivery and turnover records, which have not been provided for this article.


WHY THIS PROJECT MATTERS


A Philippine Local-Government Crematorium Reference


The Bacoor project illustrates the equipment and implementation considerations involved when an LGU develops a public crematorium: appropriate system procurement, coordinated delivery, site installation, operator preparation, and warranty coverage. It also highlights the importance of separating an equipment supplier’s scope from the construction of a broader municipal memorial complex.


PLANNING A SIMILAR PROJECT?


Living Roots Philippines supports local governments, memorial park developers and crematorium operators planning human cremation infrastructure. Discuss your project requirements, equipment options, site conditions and implementation scope with our team.



Comments


Commenting on this post isn't available anymore. Contact the site owner for more info.
bottom of page